Fish
Lake Rd. Campus - Phase 2 Site Views and Architectural Drawings
Click
the pictures below for full size versions.

Primary/Intermediate
Buildings Site View

Middle
School Site View

Fish
Lake Rd. Campus Site Plan
|
|

Intermediate
School Addition
|

Middle
School 1st Floor
|

Middle
School 2nd Floor
|
RuckPate
Architecture
Construction
Updates
11/21/05: School board update
Intermediate building - Next months work includes;
enclosing the building (trusses, roofing, windows,
temporary doors) so work can continue during the winter
Middle School - Next months work includes;
enclosing the building, floor slabs in mid-Dec., temporary
enclosures, gym masonry, trusses
Alternate folding partititions bid accepted for stage
includes back curtain, pivoting sides, and ceiling
boarders. One more bid package remains for landscaping
and road widening plans are off to the county.
11/07/05: School board update
Bids for the following were accepted as-is: Gypsum/tile,
polyboard, metal lockers, bleachers, elevator, site
utilities, and wood floors
- 10/17/05:
School board update
Intermediate
building - HVAC, electrical, concrete underway.
Masonry exterior 80% complete, interior 20% complete.
Shingles, mechanical, sprinkler, and windows by end
of October. Pushing to get enclosed and heated for
interior trades as weather turns. To-date, $9,650
in change orders.
Middle School - Action taken on bid packages
for counters, ceilings (alternate upgrade the same
as Intermediate building passed), painting, athletic
equipment, playground equipment, flooring, food service
equipment, and paving. Footings and foundations 90%
complete. Steel and masonry walls 50% complete in
classroom areas. W/in a month, exterior masonry and
floors complete. W/in 4 months, mechanical, electric,
sprinklerl. To-date, $134,285 in change orders (largely
due to one mis-bid).
Widening/turn lanes for Nippersink Rd. is the only
outstanding bid. In general, the projects are still
on time and slightly under budget. Water service from
Round Lake is still tied up in letters being sent
between Big Hollow, Round Lake, and JAWA.
- 09/19/05:
School board update
Intermediate
building - Concrete is complete. Carpentry, trusses
start w/in a month. Steel mostly done, finished w/in
a month. Interior masonry starting w/in a month.
Middle School - Concrete is 95% complete, to
be finished w/in the month. Exterior masonry to start
this week. Plumbing, electrical, HVAC bids passed.
- 09/12/05:
Architectural drawings updated
Updated versions of the following drawings from the
architects have been posted; Intermediate School floor
plan, Middle School floor plans (1st, 2nd), Middle
School view, Site Plan
- 08/13/05:
Building Committee update
Intermediate building - Site work will be complete
by August 15. Foundation excavating is complete and
concrete is being poured now. Masonry will begin the
week of August 15. Fencing will be installed to seperate
construction site activities from the Primary building
before school opens. Bid packages received to-date
are still coming in at or below budget. The Intermediate
building is still scheduled for completion August
16, 2006.
Middle School - Grading is complete. The construction
trailer has been place on-site. John Zervic will be
the project supervisor. Final interior design work
will be completed by August 16. Bid packages will
be going out the week of August 15.
- 07/18/05:
School board update
Steel and masonry decisions were approved. Concrete
decision was tabled.
- 07/12/05:
School board update
Grading and excavation has begun!
- 07/10/05:
School board update
Final permits for excavation have been received. Silt
fencing recently installed and excavation equipment
moved onsite. Grading and excavation work tentatively
scheduled to begin on Monday, July 11.
- 06/03/05:
School district newsletter update
Grading and excavation work on the Fish Lake Campus
is tentatively scheduled to begin on Monday, June
13.
- 06/01/05:
General updates
The Technology Committee, which has been reestablished
by the school board, reviewed plans for various technologies
in the new Intermediate and Middle school designs.
Feedback was given and minor revisions were noted
for computer classrooms and computer connections.
Further details will be presented to the school board
at the next meeting.
This week site markings continue to be made, construction
management/architect signs have gone up, and a construction
trailer has been moved onsite. It is anticipated that
the construction driveway may be put in this week
as well. Construction permits are estimated for June
7 - 15 and when the construction management company
gets the okays, they will begin work onsite.. The
current anticipated groundbreaking date remains June
15.
- 05/17/05:
General updates
Buffering of additional wetland area near Wilson Rd.
is being worked on with the county. A partial variance
has been pursued due to the amount of blacktop required.
Upcoming meeting with Dept. of Transportation on driveway/turn
lanes will be held. The current anticipated groundbreaking
date is June 15.
- 04/29/05:
School district newsletter update
The School District is continuing to proceed through
the "permit process" with the various required
Lake County governmental agencies. The current anticipated
timeline for the start of construction is approximately
June 1.
- 03/25/05:
School Board Update as of 3/23
Intermediate building: All bids, except components
common to both buildings including grading, paving,
and landscaping, have been received. As the bids came
in under budget, the school board voted on the following
alternate upgrades: chiller/dumpster cement block
enclosure for Primary and Intermediate buildings (approved),
ceiling tile upgrade (approved), and locker upgrade
(not approved). The school board approved the design
with the alternates.
Middle School building: Design is in progress (charts
displayed at the meeting) and will be reviewed with
teachers soon. Bidding will be in three phases. Three
areas in the design will allow for future expansion.
The school board did not approve building out the
expansion areas at this time. The estimated completion
date is December 2006.
An additional 432 parking space will be available,
for 500 total when the campus has been completed.
- 03/04/05:
School district newsletter update
The
legal notices requesting contractors to submit proposals
have been issued. Proposal approvals will be on the
March School Board agenda.
- 02/25/05:
School district newsletter update
The
sale of the building bonds for the two new schools
was completed last week. The legal process of seeking
bids for the various building construction components
(plumbing, electrical, etc.) will begin next week.
The school district continues to work with the different
county departments to secure the required permits.
- 01/19/05:
School Board Update as of 01/17
Updates
coming
- 11/17/04:
Initial Update
Very
soon after the building referendum was passed on Nov.
2, preliminary activities around construction of the
new intermediate and middle school buildings on the
Fish Lake Rd. campus began.
While there is little visible evidence at this point,
the school board has started the process with a number
of pre-construction activities on the financial and
construction aspects of the project. A subcommittee
has been appointed to oversee the construction process,
consisting of school board members Vicki Gallichio
and Todd Wright. Efforts with district contacts for
financing, architecture, and construction management
have begun. Some meetings have occurred and more have
been scheduled. Work is also being done to move through
a rigorous permitting process with the county
|
Building
Referendum
November
2, 2004
|
|
|
|
|